Изображения страниц
PDF
EPUB

to be made at a stipulated price per linear foot for excavating the tunnel, inclusive of the necessary temporary timbering, and at a specified rate per cubic yard for the concrete lining in place. Work under the contract was begun November 18, 1922, and was fully completed December 11, 1923. Both the contractor and the subcontractor were paid in full for all concrete installed, and at the contract rate per foot for the tunnel, and also for certain small extras in respect to which there was no dispute.

The controversy arises in this way: A paragraph in the specifications reads: "Part of the tunnel excavation at each end is expected to be in earth formation, and the remainder in solid rock, with possibly a short distance in loose rock, or a combination of all three." And the cross-sectional drawings conform to this expectation or assumption. In the very early progress of the work, however, the plaintiff encountered a formation of unusually fine, loose, sand, which turned out to be continuous along the line of the tunnel for most of the way. It being impracticable to carry on the work in the manner originally contemplated, or to install the concrete lining strictly in accordance with the specifications and drawings, plaintiff laid the matter before the railroad company's engineer in charge, who in turn called for directions from his superiors. The upshot was that, following a conference upon the ground, between the chief engineer and two other engineers for the railroad company, and plaintiff, plaintiff was given new specifications, pursuant to which he prosecuted the work to completion. Under these specifications the concrete lining was made thicker, the tunnel bore was correspondingly enlarged, and very much more extensive timbering was required, most of which was necessarily left in the structure.

Plaintiff was paid extra for only the additional concrete, and his claim now in controversy is for the reasonable cost, said to be approximately $73,000, of the extra tunnel excavation and timbering required by the new specifications. Under the terms of the contract the price per linear foot of tunnel excavation was for all kinds of material without classification, and was to "include all temporary shoring or timbering necessary to support the tunnel while permanent lining is being placed." All such timbering was to be removed by the plaintiff before the concrete lining was placed, "unless the nature of the material encountered made it advisable, in the opinion of the railroad company's engineer," to allow certain timbering to remain.

Plaintiff concedes that the timbering done was, under the circumstances, necessary to enable him to place the concrete lining, and that it was wholly impracticable to remove it.

[1] In his complaint, plaintiff pleads his claim in two separate counts, the first as upon an express contract, and the second upon an implied contract. Trial by jury was duly waived in writing, and upon hearing the evidence the court dismissed the action. The evidence being conflicting, and having been resolved against the plaintiff, upon the question of an expressed promise to pay, he has here abandoned his first count or cause of action, and accordingly now relies solely upon the theory of an implied promise. It should be added that he seasonably presented a motion for judgment, which was denied, and also a motion for special findings of fact, with like result, and hence our review extends within certain limitations to a consideration of the evidence. Griffin v. Thompson (C. C. A.) 10 F. (2d) 127; Bank v. Fidelity & Deposit Co. (C. C. A.) 299 F. 478. [2, 3] First, the liability of the railroad company: True though it may be that it was without conclusive knowledge of the character of the formation when it let the contract, we are of the opinion that the language above quoted from the specifications is to be taken as a representation or assurance on the part of the railroad company upon which plaintiff had the right to rely. These specifications were prepared by the company, and, if ambiguous, are to be construed against it. In form it may be conceded the language is not a positive declaration of fact; but we are concerned with the effect, rather than form, and we are to assume that some meaning was intended. The only conceivable purpose of inserting the statement must have been to influence bidders and affect bids; but, if not taken as a definite assurance respecting the character of the formation, how was it expected it would influence a rational bidder? Or are we to believe that it was inserted with the thought that thereby bidders would be induced to assume that the railroad company had information, not available to them, which gave to the "expectation" a trustworthy basis, upon which it would be safe to bid? This view we should be loath to adopt, for, inasmuch as the company had no such information, it would necessarily imply an intent to deceive.

As we read the language, it was equivalent to saying to prospective bidders or contractors, "You may bid in the expectation," or, "In submitting your bids and in contract

21 F.(2d) 1

́ing, you may assume, that part of the tunnel excavation will be in earth formation and the remainder will be in solid rock, with possibly a short distance in loose rock, or a combination of all three; and by referring to the accompanying drawings you will see that the design is suited to such, and only such, a formation." So read, it constituted a warranty.

[4] With this construction in mind, we pass to a consideration of subsequent occurrences. Upon the discovery of the true nature of the formation, the impracticability of proceeding in accordance with the contract was recognized upon all hands. It is not highly material that plaintiff did not exercise the right to rescind, or that the suggestion that he be furnished with new specifications, satisfactory to the railroad engineers, came from him, or that he was willing or desired to finish the job. Nor is it important that up to this time there were no contractual relations between him and the railroad company. The company had expressly consented to the subcontract, and through its engineer in charge was directing and supervising plaintiff's work as subcontractor. It did not accept the unexpected formation as sufficient ground for abandoning the project; it wanted the tunnel, whatever might be the formation. Through its chief engineer and his associates it dealt directly with the subcontractor, and provided him with the requested plans to meet the unexpected emergency. While it did not in expressed terms direct him to proceed, it desired that he proceed, and plainly gave him so to understand. Thus, for its benefit, it expressly or impliedly authorized him to enlarge the tunnel bore, measurably to increase the thickness of the concrete lining, and to do extensive timbering in excess of what was contemplated by the original contract. It recognized his right to compensation for the concrete and paid for it but declined to pay for the extra excavation and timbering.

It thus appearing from the unconflicting evidence that the work in question was beyond the calls of the contract, that it was done under the direction and with the approval of the railroad company, and that it resulted in a benefit to it, which it retains, there remains the inquiry whether it knew, or should have known, that plaintiff expected to be paid therefor. Page on Contracts, § 1459. In his testimony that, at the time the plans were adopted, the company's engineer promised compensation, the court below, as we learn from the memorandum opinion, thought plaintiff was mistaken, and,

there being a conflict, we do not consider such testimony. But the further important conclusion stated in the opinion, that plaintiff continued with the work and completed the tunnel without making protest or demand for extra pay, is clearly against the evidence. Kirkbride, the engineer for the railroad company, within whose jurisdiction it was to let the contract and to supervise the work, testified that, upon a visit at the tunnel site about the 1st of August, claim was made for the so-called extra work now in controversy. So that, admittedly from that time on, at least, the company knew that for the work he was doing plaintiff was expecting extra pay.

But we think it should have known at an earlier date. It is not a case of a slight change of plans, or the substitution of one plan for another, with little or only doubtful effect upon the cost of performance. Radical changes in construction were required, the additional cost of which all must have at once realized would be very great. As one of the engineers put it, cost was a secondary consideration; the construction must be safely carried out to meet the unexpected condition. Could the railroad company reasonably conclude that the plaintiff, who was under no obligation to proceed unless compensated, would gratuitously go forward with the work at a loss of $200 per day, or $6,000 a month, or an aggregate of more than $70,000 on a $140,000 job? True, it would have been better for plaintiff to have declined to proceed without a definite agreement in writing, but we do not think that, under all the circumstances, his want of caution amounted to a waiver, or should be held to have deprived him of a valuable right. Looking backward, we may see a want of care or foresight in most business transactions that result in litigation. The railroad company, too, was under some obligation to make its position clear. What response, if any, it made when admittedly in July or August it was expressly informed of plaintiff's claim, the record does not disclose; but it did not stop the work.

[5] Touching the defense based upon that clause of the contract which provides that the contractor should not be entitled to any payment for extra work, unless the work was previously authorized in writing by the railroad company, we do not deem it necessary fully to consider whether or not the provision is at all applicable, in view of the breach of warranty respecting the character of the formation and the admitted change of plans, or whether there was an effective waiv

er.

Wood v. City of Ft. Wayne, 119 U. S. 312, 7 S. Ct. 219, 30 L. Ed. 416; The Sappho (C. C. A.) 94 F. 545; Wyandotte & D. R. Ry. Co. v. King Bridge Co. (C. C. A.) 100 F. 197; Passaic Valley, etc., v. Holbrook (C. C. A.) 6 F. (2d) 721; Bartlett v. Stanchfield, 148 Mass. 394, 19 N. E. 549, 2 L. R. A. 625; Wyman v. Hooker, 2 Cal. App. 36, 41, 83 P. 79; Jobst v. Hayden, 84 Neb. 735, 121 N. W. 957, 50 L. R. A. (N. S.) 501. After the conference in January between the three railroad engineers and plaintiff, pursuant to the conclusion there reached the engineer in charge prepared and furnished to the plaintiff drawings showing in detail what plain

tiff should do. If it be assumed that the contract clause is applicable, and was not waived, these drawings, we think, under the circumstances met its requirements.

As to the Utah Construction Company, we conclude, with the lower court, that no liability is shown. It was not represented at the January conference, had nothing to do with the new plans, and received no benefit from the work. As to it, therefore, the plaintiff's complaint was properly dismissed. In view of the uncertainty as to the status of its counterclaim, however, and to the end that there may be but one judgment in the case, we deem it better to reverse the entire judgment, with instructions to enter a judgment upon the record as it stands, in favor of plaintiff and against the railroad company, for the reasonable cost of the extra work called for by the new plans, exclusive of the concrete, which has already been paid for, the cust to include a reasonable compensation for plaintiff's superintendence, and dismissing the plaintiff's complaint against the construction company, with appropriate disposition of the construction company's counterclaim against plaintiff.

And such will be the order, with costs in this court to plaintiff against the railroad company and to the construction company against the plaintiff.

BACKUS-BROOKS CO. v. NORTHERN PAC. RY. CO. et al.

Circuit Court of Appeals, Eighth Circuit. June 15, 1927.

No. 7602.

1. Corporations 320(3)-Minority stock holder's cause of action for directors' failure faithfully to serve stockholders held equitable, and doctrine of laches applied to time of commencement of suit.

Cause of action of minority stockholder in railroad corporation, suing on behalf of corpo

ration, based on proposition that directors were elected and dominated by defendant, another stock, and that directors operated corporation railroad, which controlled all corporation's for benefit of defendant, instead of for corporation's stockholders, held within exclusive jurisdiction of equity, stockholder's interest in corporation, and in conduct of its officers affecting its property, being equitable and not legal, and doctrine of laches, and not statute of limitations, applied to time of commencement of suit.

2. Corporations

209-Stockholder must sue

on behalf of corporation within reasonable time after acquiring knowledge, or be barred by laches.

behalf of the corporation, must act promptly

A stockholder, who undertakes to sue on

after acquiring knowledge of the conditions of which he complains, and if he stands by with knowledge of the facts for an unreasonable time his right to maintain such a suit will be barred by lachęs.

3. Corporations 212-Minority stockholder, suing for corporation on wrongs occurring over 6 years before filing bill, had burden of showing application of doctrine of laches inequitable (Gen. St. Minn. 1923, § 9191).

Where wrongs asserted by minority stockholder of railroad as basis for stockholder's suit on behalf of corporation occurred more than 6 years prior to filing of bill, burden was on such stockholder to allege and prove facts which would make it inequitable to apply thereto the doctrine of laches by analogy to 6-year limitation of Gen. St. Minn. 1923, § 9191.

[blocks in formation]

6. Corporations 209-Minority stockholder, not excusing 12 years' delay in preparing and submitting claims under arbitration agreement, held barred by laches from recovering on claims arising 6 years before suing (Gen. St. Minn. 1923, § 9191).

of a railroad corporation, and defendant, a conWhere complainant, a minority stockholder necting railroad, entered into an agreement to arbitrate minority stockholder's claims that officers and majority of directors of complainant's railroad operated complainant's railroad for defendant's benefit, and that the arbitration should be had after a firm of outside ac

21 F.(28) 4

countants should make audit of defendant's books and report to minority stockholder, held, that claims arising 6 years before filing of suit were barred by laches, where complainant alleged no facts excusing delay of 12 years in suing, nor gave any reasons why it took accountants 12 years to make investigations and report, nor alleged that defendant hindered or prevented complainant in investigating and preparing its claims, in view of Gen. St. Minn. 1923, § 9191.

7. Arbitration and award 16(4)—In ab. sence of provision for filling vacancies, death of one arbitrator named in agreement and incapacity of other revoked submission.

Where arbitration agreement named one arbitrator and one alternate, and made no provision for filling vacancies, the death of one arbitrator and the incapacity of the other to act revoked the submission.

8. Commerce 85(5)—Statute held not to authorize Interstate Commerce Commission to award reparations on account of past divisions of joint rate voluntarily established (Transportation Act 1920, § 418, amending Interstate Commerce Act, § 15 [6], being. Comp. St. § 8583 [6]).

Where joint rate was not established pursuant to a finding or order of the Interstate Commerce Commission, the Commission had no authority, under Transportation Act 1920, § 418, amending Interstate Commerce Act, § 15 (6), being Comp. St. § 8583 (6), to award reparations to one of carriers on account of past divisions.

9. Commerce 89-Justness and reasonableness of division of joint rates in future and reparation for unjust divisions in past must first be acted on by Interstate Commerce Commission.

Questions whether division of joint rates is just, reasonable, or equitable as to future, and reparations for damages sustained on account of unjust, unreasonable, and inequitable divisions in the past, will not be considered by the courts until Interstate Commerce Commission has determined what is a just, reasonable, and equitable division of joint rates between the carriers involved.

10. Commerce 85(5)-Just division of joint rates for future is legislative question, determinable only by Interstate Commerce Commission.

Question of just, reasonable, and equitable divisions of joint rates for the future is a legislative question, which only the Interstate Commerce Commission may determine.

11. Commerce

87-Interstate Commerce Commission, on complaint of carrier, may determine division of joint rates voluntarily established (Interstate Commerce Act 1887, §§ 1, 13-15, as amended [Comp. St. §§ 8563, 8581-8583]).

Under Interstate Commerce Act 1887, §§ 1, 13-15, as amended (Comp. St. §§ 8563, 85818583), the Interstate Commerce Commission, en complaint of one carrier against another, may determine the division that each is entitled to receive out of their voluntarily established joint rates; it being the intent of Congress to provide relief to a small carrier

from an unjust division imposed on it, because of the domination of a larger connecting carrier.

12. Commerce 87-Minority stockholder of railroad may invoke jurisdiction of Interstate Commerce Commission by filing complaint charging inequitable division of joint rates (Interstate Commerce Act 1887, §§ 1, 13, as amended and re-enacted by Transportation Act 1920, $ 400, 416 [Comp. St. §§ 8563, 8581]).

Under Interstate Commerce Act 1887, § 13, as amended and re-enacted by Transportation Act 1920, § 416 (Comp. St. § 8581), minority stockholder of railroad may file a complaint with Interstate Commerce Commission charging an unjust, unreasonable, and inequitable division of joint rates between such stockholder's corporation and other carriers involved, and such a complaint so filed would properly invoke the jurisdiction of the Commission to proceed to investigate the complaint and report in writing its conclusions and decision, order, or requirement in the premises, in view of Interstate Commerce Act 1887, § 1, as amended and substantially re-enacted by Transportation Act 1920, § 400, par. 4 (Comp. St. § 8563). 13. Public service commissions 6-Powers of state commission are limited to those expressly or by fair implication included in authority expressly conferred, and reasonable doubt should be resolved against power.

The powers of a state commission are special, and limited to such authority as is legally conferred by express provisions of law, or such as is by fair implication and intendment incident to and included in the authority expressly conferred, for the purpose of carrying out and accomplishing objects for which it was created, and any reasonable doubt as to existence of any particular power in the commission should be resolved against the exercise of such power.

14. Constitutional law 62-Legislative power to fix divisions of joint rates may be delegated to state commission.

Legislative power to fix divisions of joint rates between connecting carriers for the future may be lawfully delegated to a state commission.

15. Carriers

12(2)-State statute authorIzing statɔ Railroad and Warehouse Commission to fix joint rates held by implication to authorize commission to fix division of such rates (Gen. St. Minn. 1923, §§ 4638-4641, 4644, 4700).

Gen. St. Minn. 1923, § 4700, authorizing state Railroad and Warehouse Commission to fix and establish joint rates, held by necessary implication to confer power on commission to fix divisions of such rates between the carriers; fixing of each carrier's share being part of the establishing of a joint rate, in view of sections 4638-4641, 4644.

16. Carriers 12(62)-Minority stockholder of railroad may file complaint with state commission, and on proper showing secure revision of joint intrastate rates and divisions thereof (Gen. St. Minn. 1923, § 4700).

Under Gen. St. Minn. 1923, § 4700, a minority stockholder of a railroad may file complaint with state Railroad and Warehouse

Commission, and on a proper showing secure a revision of the joint intrastate rates and divisions thereof between stockholder's corporation and other carriers.

17. Public service commissions

19/2-Fair

ness of past divisions of joint intrastate rates must be determined by state commission before judicial relief can be granted (Gen. St. Minn. 1923, §§ 4638-4641, 4644, 4700).

Before complainant can secure judicial relief on account of past divisions of intrastate joint rates, it must first apply to state Railroad and Warehouse Commission, and have the preliminary question of what is a fair division of the rates involved first determined by that commission, in view of Gen. St. Minn. 1923, 88 4638-4641, 4644, 4700.

Appeal from the District Court of the United States for the District of Minnesota; Joseph W. Molyneaux, Judge.

Action by the Backus-Brooks Company against the Northern Pacific Railway Company and others. Decree for defendants, and plaintiff appeals. Affirmed.

Thomas L. Philips, of St. Louis, Mo., and John Junell, of Minneapolis, Minn. (Ralph Whelan, Koon, Whelan & Hempstead, and Lancaster, Simpson, Junell & Dorsey, all of Minneapolis, Minn., on the brief), for appel

[blocks in formation]

PHILLIPS, District Judge. This is a minority stockholder's suit brought in behalf of the Minnesota & International Railway Company (hereinafter called the Minnesota Company), by Backus-Brooks Company, the minority stockholder (hereinafter called complainant), against the Northern Pacific Railway Company (hereinafter called the Northern Pacific), the Minnesota Company, the Minnesota Loan & Trust Company, the Big Fork & International Falls Railway Company (hereinafter called the International Company), C. W. Bunn, F. W. Sweeney, R. W. Clark, R. H. Relf, W. H. Gemmell, Charles Donnelly, Thomas Cooper, Howard Elliott, and J. M. Hannaford. The bill of complaint was filed December 22, 1923.

The Northern Pacific owns and operates a line of railroad extending from Minneapolis and St. Paul to Brainerd, Minn. The Minnesota Company owns and operates a line of railroad from Brainerd to Northome, Minn. This line was completed to Bemidji in 1898, and to Northome in 1903. The Big

Fork & Northern Railway Company (hereinafter called the Big Fork Company) owns a line of railroad from Northome to Grand Falls, Minn., which was completed in 1905. The Minnesota Company owns the stock in the Big Fork Company and operates the latter company's line of railway under lease. The International Company owns a line of railroad from Grand Falls to International Falls, which was completed in 1907. The Northern Pacific owns the stock in the International Company. It will be observed that this makes a complete line of railroad from St. Paul to International Falls, and that the Northern Pacific owns the southern ter

minus and controls through stock ownership

the northern terminus thereof.

The matters complained of in the bill may be divided into three classes:

(1) Certain acts and transactions which occurred more than 6 years prior to the filing of the bill, the details of which will be referred to more specifically hereinafter;

(2) The divisions made of earnings on joint line traffic, during the 6-year period immediately prior to the filing of the bill, between the Northern Pacific, the International Company, and the Minnesota Company;

(3) The division of expenses between the Northern Pacific, the International Company and the Minnesota Company upon comother for services, facilities, use of equipmon operations, and compensation paid each ment, repairs of equipment and the like, during the 6-year period immediately prior to the filing of the bill.

The matters falling in class 1, as alleged in the bill and in support of which complainant either adduced or tendered proof, were, in general, these:

That, in the year 1894, the complainant and certain associates acquired all of the capital stock of the Brainerd & Northern Minnesota Railway Company (hereinafter called the Brainerd Company), complainant acquiring 30 per cent., and its associates 70 per cent., of such stock; that in the latter part of the year 1899, or the early part of the year 1900, the Northern Pacific purchased 70 per cent. of the capital stock of the Brainerd Company held by complainant's associates, in violation of an agreement between complainant and its associates not to sell to any person not a stockholder of the Brainerd Company without first offering such stock for sale to the other stockholders; that, to avoid a threatened suit by complainant to set aside such transfer of stock to the Northern Pacific, the Northern Pacific agreed that it would cause the Brainerd Company's line of rail

« ПредыдущаяПродолжить »